How long does it take to build a website? Our two-week process

A small-business website takes two weeks to build when the scope is fixed in writing, the content is ready before kickoff, and approvals come back within a day. The six-to-twelve-week timelines most studios quote are mostly waiting: for copy, for photos, for someone to look at a design. Our process runs kickoff on day one, structure and copy on days two to four, design and build on days five to eight, review on days nine to eleven, and testing and launch on days twelve to fourteen.

Two weeks is our target delivery for a standard bilingual business site. E-commerce, custom features and slow approvals stretch it, and we say so before we start. Here is how the fortnight works and what you need to have ready.

Why do most website projects take two or three months?

Not because building takes that long. A ten-page site is perhaps 40–60 hours of real design and development. Projects stretch because of five things:

  • Content arrives late. The studio waits for copy and photos the client assumed were "nearly ready".
  • Nobody owns approvals. A design sits in an inbox for a week because three partners each think someone else is reviewing it.
  • Scope creeps. "While you are in there, can we add a careers page and a booking system?"
  • The studio is juggling. Your project gets attention in gaps between other projects.
  • Unlimited revisions. Without a fixed number of rounds, round four is always possible, so round one is never taken seriously.

Fix those five and calendar time collapses to working time.

What has to be ready before kickoff

We do not start the clock until these exist. It is the single biggest factor in hitting the date:

  1. Fixed written scope and price. The list of pages, languages, forms and integrations, signed off. Changes after kickoff are quoted separately and may move the date.
  2. Logo files in vector format, plus brand colours and fonts if you have them.
  3. Copy, or the raw material for it. Either finished text per page or a voice note and bullet points per page that we turn into copy. Blank pages cannot be designed.
  4. Photos. Your premises, team, products or work, at full resolution. If you have none, a shoot is scheduled in week one or we agree on stock as a placeholder.
  5. Access. Domain registrar login, or authority for us to register one in your name. Google Business Profile access if it exists.
  6. One decision-maker who can approve within 24 hours.

Studios that insist on this list before quoting are the ones who hit their dates. The same list also makes quotes comparable, as explained in what a website costs in Dubai.

The two-week schedule, day by day

Day 1: kickoff. A 60–90 minute call. We confirm the page list, agree the sitemap, review your content and reference sites, and set the two review dates in the calendar.

Days 2–4: structure and copy. Wireframes for the home page and one service page, and draft copy for every page in English, with Arabic translation starting in parallel. You review the wireframes and copy on day four.

Days 5–8: design and build. We design the home page and a service page in full, get a thumbs-up, then build every page directly in the browser. Mobile layout is built at the same time, not adapted later. Forms, WhatsApp button, maps and analytics are wired in.

Days 9–11: review and revisions. You get a private link to the full site in both languages. Two rounds of revisions are included, with each round turned around within a working day.

Days 12–14: testing and launch. We test on real phones and desktops, check load speed, fix every link, verify forms deliver to the right inbox and WhatsApp, submit the sitemap to Google, and go live on your domain. You receive all logins and files.

What stretches a website timeline, and by how much

  • E-commerce: add one to three weeks for product data entry, payment gateway approval and shipping rules. Gateway approval in the UAE depends on your trade licence and documents being in order.
  • Custom features such as booking engines, client portals or CRM integration: typically add two to four weeks and are usually scoped as a phase two.
  • Content not ready: every day of delay on copy or photos is a day on the launch date. This is the most common cause.
  • Approvals over 24 hours: same effect. A design that waits four days moves launch by four days.
  • More than 15 pages: roughly one extra day per three pages.
  • Arabic translation by a third party: allow a week and build it into the plan.

We flag which of these apply in the written scope, so the date you are given is the date you can plan around.

Can a website be built in three days?

Yes, for a focused site: a landing page or a five-page brochure site with content ready and one decision-maker on call. We do rush builds within three days for a fee, and the compressed schedule means one review round rather than two. It suits a product launch, a trade show or an ad campaign that is already booked, not a fifteen-page bilingual site with a shoot.

What happens after launch

Launch is not the end of the two weeks. We also check that the site is indexed, set up Google Analytics and Search Console, confirm conversion tracking on forms and WhatsApp clicks, and hand over a short guide to editing content. Everything is registered to you: domain, hosting, code, content and accounts.

From there you can run the site yourself, come back for changes at an hourly rate, or fold it into a monthly marketing plan that keeps it updated and sends it traffic. For the two-week date in writing, send your page list through the enquiry form; our web design page lists the full scope, and 12 things every small-business site needs covers what the finished site should contain.

Questions people ask

How long does it take to build a small-business website?
Two weeks from kickoff when scope is fixed, content is ready and approvals happen within a day. Typical industry timelines of six to twelve weeks are mostly waiting time.
What do I need to provide before the website build starts?
A signed scope, vector logo files, copy or bullet points for each page, photos, domain access and one person who can approve designs within 24 hours.
Can you build a website in less than a week?
Yes, a landing page or small brochure site can be delivered within three days with a rush fee, provided content is ready and reviews happen the same day.
What adds time to a website project?
E-commerce setup, custom features such as booking or portals, late content, slow approvals, more than 15 pages and third-party Arabic translation. Each is flagged in the written scope with its effect on the date.

Related reading

Web· 4 min read

Bilingual Arabic–English websites: how to do right-to-left properly

How to build a bilingual Arabic–English website in the UAE: true RTL layout, Arabic typography, URLs and hreflang, and the mistakes that make Arabic look wrong.

Read post →
Web· 4 min read

Why your website is slow — and what it costs you in leads

Slow websites lose leads. The common causes, how to measure yours in two minutes, what slowness costs a Dubai business in enquiries, and fixes ranked by impact.

Read post →
Web· 4 min read

WordPress vs a hand-built website for a Dubai business

WordPress or a hand-built website for your Dubai business? Honest comparison of speed, security, three-year cost, editing and Arabic, and who should pick which.

Read post →